    Submitted by Tiffany Little

    https://bugs.launchpad.net/evergreen/+bug/1869728

    In 3.4.2 we are encountering this problem:

    If a library has a normal closed date scheduled in the Closed Dates Editor (for example, April 10) and then they enter an emergency closing that encompasses that date (for example, April 5-15) and check the box to Process Immediately, the processing returns 0/0 processed but no other error message.

    #676
    Benjamin Kalish
    Participant

    Well, that sounds inconvenient.